Company milestones

company
milestones

Project Milestones

  • 2023 FEB
    Timeline
    • Environmental Impact Assessment (EIA) approved by DOE
  • 2023 MAY
    Establishment of Taiyokoko Malaysia
    • Establishment of TAIYO KOKO MALAYSIA SDN. BHD.
  • 2024 JAN
    Timeline
    • Environmental Management Plan (EMP) approved by DOE
  • 2024 JULY
    Timeline
    • Written Permission (WP) approved by DOE
  • 2024 DEC
    Timeline
    • Construction begins
  • 2025 JUNE
    Timeline
    • Manufacturing License approved by MIDA
  • 2025 NOV, 12
    Timeline
    • Signing Ceremony with Kobe Steel, Ltd. for its contribution to Taiyo Koko Malaysia

Future Schedule

Mechanical Completion expected
END OF 2026

Mechanical
Completion
expected

Test operation to commence
Q1 2027

Test operation
to
commence